FIGARO project timeline (2012–2016)
This timeline is our reconstruction, built from the project's dated announcements.
- October 2012 Project start (FP7, grant agreement 311903, 48 months).
- February 2013 EU grant of about €6 million announced; consortium led by Netafim.
- June 2013 Partners meeting in Kavala, Greece; prototype field tests under way in nine countries.
- January 2014 Valencia meeting: first full season of field results; cotton case study.
- June 2014 Presentations at the World Processing Tomato Congress and the CommNet round table.
- November 2014 EIP Water Conference, Barcelona.
- January 2015 Platform version 1 presented at FAO, Rome.
- March 2015 Field data retrieval web service and WiseUp tool.
- July 2015 Results presented at ECPA 2015, Tel Aviv.
- January 2016 Annual meeting in Bologna to prepare the demonstrations.
- March–July 2016 Workshops and open field days in Greece, Denmark, Spain, Italy and Portugal.
- June 2016 Final platform presented in Kavala.
- September 2016 Haifa conference and Zar'it field day (7–8 Sep), Komotini field day (14 Sep), closing conference in Brussels (19 Sep).
- 30 September 2016 End of the project.